Tomorrow I will meet with a potential associate to discuss a possible job
for
architectural ironwork for a real estate developer. So far all I know is
that
the development is about $135M worth, not a bad chunk of change.
What I would like to know from those of you that have done this sort of
thing
before (i.e. bidding on such a project) is: what proportion of the total
(in
this case $135M) cost of these projects does the ironwork account for? I'm
looking for typical figures. I know the REAL answer is "it depends". I
just
would like a ballpark notion, i.e. would it typically be closer to .5% or
5%,
to pull numbers off the top of me pointy. I would like to go into this
meeting
without being completely surprised one way ot the other.
Thanks much.