Andy,
That's a tough one. I have everywhere from as low as .5% to as high as
1.5% and everywhere in between.
The variables are the obvious, how many lineal feet per house, how
detailed a design, etc.
I think you would be far better off quoting on a per foot basis. I know
all the big commercial shops around here like Stewart do not quote
except by the lineal foot.
Ray Miller
Cincinnati
On Sunday, November 2, 2003, at 03:33 PM, Demon Buddha wrote:
> Folks,
>
> Tomorrow I will meet with a potential associate to discuss a possible
> job for
> architectural ironwork for a real estate developer. So far all I know
> is that
> the development is about $135M worth, not a bad chunk of change.
>
> What I would like to know from those of you that have done this sort
> of thing
> before (i.e. bidding on such a project) is: what proportion of the
> total (in
> this case $135M) cost of these projects does the ironwork account for?
> I'm
> looking for typical figures. I know the REAL answer is "it depends".
> I just
> would like a ballpark notion, i.e. would it typically be closer to .5%
> or 5%,
> to pull numbers off the top of me pointy. I would like to go into
> this meeting
> without being completely surprised one way ot the other.
>
> Thanks much.
>
> -Andy
> _______________________________________________
> http://mailman.qth.net/mailman/listinfo/theforge
> theforge mail list group photo site is
> http://www.photoaccess.com
> Login: [email protected]
> password: anvil
> ___________
>
>