Would appreciate clarification of several items:
1. Regarding placement of lock washers, on page
12 of the manual it indates that on the ATU
control board, the spacers are supposed to be
between the PC board and screws; this is contrary
to what's indicated on page 6 of the manual and
contrary to what 26 Feb 2000 KAT2 Builder Alert.
Am I correct that the intention here is to place
spacers between the standoffs and the PC board
with respect to BOTH the ATU control board and
the L-C board? (So its screw - atu board -
spacer - standoff - spacer - LC board - screw?)
2. I assume the reference in the first step on
manual page 12 to RF-P3 as mating to the ATU
connector J7 is a typo; the correct reference is
supposed to be to RF-P6?
3. On page 11, the third to last step is supposed
to be solder the braid and center conductor at
one end of the coax cable to the pads labeled
"GND and RF" (vice "RF and GND"), right?
Thanks,
Paul N6LQ