[Elecraft] Re: build rate?

Eric Swartz - WA6HHQ, Elecraft eric at elecraft.com
Tue Jan 22 12:34:15 EST 2008


Don's numbers are incorrect (way on the low side). :-)

73, Eric

===
Brett Gazdzinski wrote:
> They are working 7 days a week, and getting 15- 20 K3's
> built a week, thats 2-3 radios a day?
>
> ...
>
> Thanks,
> Brett
>
>
>
>
> If you want to "know the numbers", Elecraft is currently shipping 15 to 
> 20 K3s per week, and if the shipping date for current orders is 
> mid-April, then there is somewhere between 255 and 340 K3s on order 
> right now - simple calculation reveals that result - what more 
> information do some folks need?
>
> 73,
> Don W3FPR
>   


More information about the Elecraft mailing list